Wednesday, September 15, 2010

Framing continues . . .

Framing continues


We're 3 or 4 weeks into framing and all is going well. Click on picture above for new collection of framing photos.

Monday, August 23, 2010

Framing 1st Week


Framing has begun with Jeremy's crew working fulltime on the project. Some tweaking of plans is continuing as well as decisions about plumbing and fixtures. Click picture below to see a batch of framing pictures.





Framing 1st week

Tuesday, July 13, 2010

Concrete Wall

The concrete retaining wall is in. Man, that thing is huge. Handball, anyone? Check the photos:
Retaining Wall and Floor Joists

Friday, June 4, 2010

House Plans and Week 3 Photos



Almost finalized floor plans above. Sill working on the layout of the second floor of the main building. Other details are being resolved, but thought we should share these now that construction is underway.

Well drilling started today and should finish by early next week. We met Jeremy at a house project he is currently finishing to make a decision about concrete floor finishing. During our conversation there, he mentioned that framing would start within the next 3 weeks. Moving along pretty well, because the weather has been uncharacteristically nice for Vermont.

Also posted more photos from week 3 : click here


Friday, May 21, 2010

Concrete Days

Anchor Foundations arrived on Wednesday and concrete is happening. I stopped by after work today and they were placing the forms for the basement. I’m amazed by how different things look as the footprint for each of the structures becomes defined in 3 dimensions. When we met with Rolf and Jeremy on Monday they told us that throughout the process we’ll have different perceptions of the space—and that this happens in all projects. There’s a shift between things looking too big to seeming too small and back again. And we eventually end up (hopefully) with the space feeling just right. Kind of like Goldilocks and the 3 bears.

Well, this process started for me today. The foundation hole was seeming HUGE to me on Tuesday — and now that the forms are going in, it’s looking much smaller. . . glad I was forewarned of this process. More photos are here http://picasaweb.google.com/tinacvt/VillaVerdeConstructionWeek2#


Sunday, May 16, 2010

Another Planet


Stevie (in the photo) and I went out to the land this morning — the dirt piles keep growing! The basement hole looks complete — and massive to me right now. The landscape is so altered, that it felt almost as though we were on another planet. With great weather forecast for the entire week the concrete work will commence! I’m hoping to swing by during the day to get photos of work in progress.

I’m also in the process of creating spreadsheets for our bathroom and kitchen fixtures and lighting. Hoping to have most of that complete by June 1st, so that things can keep moving, especially since I’m entering my busy season at work.

More later.



Thursday, May 13, 2010

Let the Games Begin


I can’t seem to stay away from the land now that things are happening. Ran out there after work again tonight to see what progress had been made. I’m finding lots of things to photograph out at the building site. Take a look at them here:

http://picasaweb.google.com/tinacvt/VillaVerdeConstructionWeek1#

The first few photos are of a model that Rolf had one of his interns build. We hope to post floorplans sometime soon.